A 3.1 certificate is the most misread document in a stainless order. It records the results of specific inspection on one heat, validated by the mill's own inspection representative. It does not prove that the plate in front of you came from that heat, that the surface finish is right, or that anyone witnessed the tests on the buyer's behalf. Those are separate checks, and they fail separately.
Four document types hide behind one word
Buyers ask for "a certificate" and suppliers answer with whatever their system issues. EN 10204 separates them by who validates the results, not by how official the letterhead looks.
| Type | What it states | Who validates |
|---|---|---|
| 2.1 | Compliance with the order, no test results | The manufacturer |
| 2.2 | Compliance plus results of non-specific inspection | The manufacturer |
| 3.1 | Specific inspection results for the material supplied | The manufacturer's authorized inspection representative, independent of the production department |
| 3.2 | The same specific results, countersigned | That representative plus the purchaser's representative or an inspector designated by official regulations |
The distinction that matters in a dispute is the word "specific". A 3.1 ties the chemistry and mechanical results to the heat being delivered. A 2.2 can be built from inspection that was never run on that heat. Asking for "MTC" without naming the type leaves that choice to whoever prints the document.
Three places the heat number has to agree
Traceability is a chain, not a page. The heat (or cast) number has to match in three places: on the certificate, on the shipping mark of the bundle, crate or coil tag, and on the marking of the material itself where the form allows it.
Cut sheet, slit strip and small fittings are where the chain usually breaks. Once a coil is slit into narrow widths, the individual strips often carry no marking at all, and the link back to the parent heat rests entirely on the cutting record and the package labels. Agree how that link is kept before the material is cut. Reconstructing it after the parts are mixed on a fabrication bench is not possible, and no certificate can do it retroactively. The quality control page lists where that handover sits in the order sequence.
Where 3.1 stops and PMI starts
The certificate describes a heat. Positive material identification describes the piece sitting in front of the inspector. A handheld XRF analyser reads chromium, nickel and molybdenum in seconds, which is enough to catch a 200-series substitute or a plate sold as 316L. It does not read carbon, and it does not report nitrogen reliably. So the L in 304L, and the nitrogen contribution in a duplex grade, still come from the heat analysis behind the certificate.
That division belongs in the purchase order. "PMI on every piece" checks identity; it does not check thickness tolerance, surface finish or heat treatment. A certificate checks the heat; it does not check which pallet was loaded. Run both and the two gaps close. For the 304 composition limits, the standard is the reference, not the number printed on the gun.
A 3.1 cannot be turned into a 3.2 later
A stockholder cannot upgrade existing paperwork by adding a stamp. Type 3.2 requires the witnessing and validation arrangement to be in place when the inspection happens, with the purchaser's representative or a designated inspector involved. If the project specification calls for 3.2, say so at enquiry stage, because it changes who has to be present and when the material can be released.
The same applies to fabricated assemblies. A certificate for the parent sheet does not automatically cover the tube, flanges and fasteners bought separately, nor does it cover the finished weld. Keep the certificate scope and the product scope in separate lines of the order. The stainless RFQ guide shows where those lines sit.
Clauses that survive a claim
| Put this in the order | Why it earns its line |
|---|---|
| EN 10204 type 3.1, tied to each heat | Fixes who validates and what is tested |
| Grade, UNS designation and product standard with edition | Gives the chemistry something to be checked against |
| Marking method for cut pieces and slit strip | Preserves the heat link after processing |
| PMI scope and acceptance elements | Separates identity from the rest of the inspection |
| Whether a 3.2 witness is required | Cannot be arranged after the fact |
The 3.1 that travels with each batch is one link in that chain, not the whole chain. Ask for the heat number and the marking method before anything is cut. Once the offcuts lose their tags, the argument is about recollections rather than material.